Client Details
Project Details
Client Brief
This specification sheet is based on an initial meeting with Robert Richman on Tuesday 11th Oct 2022.
And a subsequent meeting with Rob & Nicole on Monday 31st October 2022, & on Wed 16th Nov 2022.
This spec is based on the original plan although the client has provided a new upstairs layout which he is aware will impact on certain prices below.
We have compiled this job spec based on your current requirements however, should you wish to make any amendments post project commencement, these will be detailed in an additional services sheet with the relevant additions / subtractions to the price.
Due to the on going pandemic and the subsequent issues to the global supply chain, we will endeavour to make the client aware at the earliest opportunity of any price increases to materials which cannot be reasonably absorbed within the original contract price.
If Asbestos is found during the contract this is chargeable, for safe removal and disposal by Approved Asbestos Contractors.
We have provided a nominal figure for the number skips required to complete the job, however should more be required this will be at the client's cost.
TENDER PROCESS
- ESTIMATE STAGE - Based on 1 site visit and brief discussions with client
- SPECIFICATION STAGE - Following a further site visit and detailed discussion with client, including any visits to preferred suppliers
- FINAL SPEC & CONTRACT - Once client is completely satisfied with full spec for the project
Schedule of Works
| Phase | Description | Start | End | ||
|---|---|---|---|---|---|
Services Specification
General Estimated Costs
| Item | Description | Estimated | ||
|---|---|---|---|---|
| Muckaway | ||||
| Waste Removal | ||||
| Plasterboard Removal | ||||
| Inert Waste Removal | ||||
| Asbestos Pre-Refurbishment Survey & Removal | ||||
| WC - Welfare Facilities | ||||
| Site Security - Heras Panels with Stabilisers, Feet & Clips | ||||
| Tree Protection (Ground Guard) | ||||
| Bat Conservation | ||||
| Drainage Survey - CCTV | ||||
| Lifting / Propping Equipment (Cranes, Hi-Abs & Genie Lifts) | ||||
| Plant Hire (Diggers & Dumpers, Forklifts, Concrete Pumps) | ||||
| Scaffolding | ||||
| Floor Protection | ||||
| Property Services (Gas, Electric, Water - new connections & meter moves) | ||||
| Building Inspection | ||||
| CDM - Fire Risk Management Plan | ||||
| Total (included items) |
Labour Estimated Costs
| Item | Description | Estimated | ||
|---|---|---|---|---|
| General Site Labour | ||||
| Demolition & Site Prep | ||||
| Groundworks | ||||
| Drainage | ||||
| Sub & Super Structure | ||||
| Structural | ||||
| Carpentry - Roofing | ||||
| Carpentry - Exterior Plastics | ||||
| Roofing | ||||
| Fenestration | ||||
| Insulation & Vapour Barrier - Floor | ||||
| Floor Screed | ||||
| Under Floor Heating | ||||
| Electrics | ||||
| Satellite & Aerials | ||||
| Alarm Systems | ||||
| Ventilation & Mechanical Extraction | ||||
| Renewables - Solar Panels & Battery Storage | ||||
| Plumbing - Hot, Cold & Waste | ||||
| Plumbing - Heating | ||||
| Plumbing - Sanitary-ware | ||||
| Water Softener | ||||
| Carpentry - 1st Fix | ||||
| Carpentry - 2nd Fix | ||||
| Carpentry - Internal Doors | ||||
| Carpentry - External Doors | ||||
| Carpentry - Kitchen & Utility | ||||
| Plastering | ||||
| Metal Frame Ceilings | ||||
| Insulation - Walls & Ceilings | ||||
| Rendering | ||||
| Fireplaces & Log Burners | ||||
| Air Conditioning | ||||
| Technology | ||||
| Stairs | ||||
| Balconies & Railings | ||||
| Tiling | ||||
| Fitted Furniture | ||||
| Flooring | ||||
| Decorating | ||||
| Mastic & Sealants | ||||
| Finishing & Cleaning | ||||
| Total (included items) |
Material Estimated Costs
| Item | Description | Estimated | ||
|---|---|---|---|---|
| Labour | ||||
| Demolition & Site Prep | ||||
| Groundworks | ||||
| Drainage | ||||
| Sub & Super Structure | ||||
| Structural | ||||
| Carpentry - Roofing | ||||
| Carpentry - Exterior Plastics | ||||
| Roofing | ||||
| Fenestration | ||||
| Sub-floor | ||||
| Under Floor Heating | ||||
| Electrics | ||||
| Satellite & Aerials | ||||
| Alarm Systems | ||||
| Ventilation & Mechanical Extraction | ||||
| Renewables - Solar Panels & Battery Storage | ||||
| Plumbing - Hot, Cold & Waste | ||||
| Plumbing - Heating | ||||
| Plumbing - Sanitary-ware | ||||
| Water Softener | ||||
| Carpentry - 1st Fix | ||||
| Carpentry - 2nd Fix | ||||
| Carpentry - Kitchen & Utility | ||||
| Carpentry - Internal Doors | ||||
| Carpentry - External Doors | ||||
| Plastering | ||||
| Metal Frame Ceilings | ||||
| Insulation - Walls & Ceilings | ||||
| Rendering | ||||
| Fireplaces & Log Burners | ||||
| Air Conditioning | ||||
| Technology | ||||
| Stairs | ||||
| Tiling | ||||
| Fitted Furniture | ||||
| Flooring | ||||
| Decorating | ||||
| Mastic & Sealants | ||||
| Finishing & Cleaning | ||||
| Total (included items) |
Before
During
After
General Costs
Materials
Labour
Sundries
| Date | Item / Description | Supplier | Ref / Invoice # | Net | VAT | inc VAT | Receipt / Invoice |
|---|
Client Direct Payments
| Date | Source | Item | Supplier / Payee | Original Est. | Client Paid | Service Fee | |
|---|---|---|---|---|---|---|---|
| No client direct payments logged yet. Click Add Payment to record one. | |||||||
| Totals | -£0.00 | £0.00 | £0.00 | ||||
Project Notes
Additional Services / Extras
| Description | Added | Amended | Client Approved | Stage | Cost | Net Price |
|---|---|---|---|---|---|---|
| Asbestos Testing - 6no. areas on 24hr turnaround | 12/01/2023 | - |
Yes
| £280.00 | £329.00 | |
| Flue Liner - Removal of existing system, install cowl | 18/01/2023 | - |
Yes
| £335.00 | £394.00 | |
| Design Bureau - SE Specification | 22/01/2023 | - |
Yes
| £345.00 | £405.00 | |
| Building Control Sign-Off - Structural changes | 25/01/2023 | - |
Yes
| £245.00 | £288.00 | |
| Floor removal - glued down oak in dining & bedrooms | 02/02/2023 | - |
Yes
| £200.00 | £235.00 | |
| Carpentry extras - Caberdek, door linings, acoustic insulation, loft ladder | 08/02/2023 | 15/03/2023 |
Yes
| £6,090.00 | £7,155.00 | |
| Electrical extras - WC mirror, sensor lights, stair lighting, additional wiring | 14/02/2023 | 20/04/2023 |
Yes
| £2,808.00 | £3,300.00 | |
| Staircase - Change supplier + stringer LEDs + protection | 05/03/2023 | - |
Yes
| £1,361.00 | £1,599.00 | |
| Windows - Replacement sealed units & servicing | 18/03/2023 | 10/04/2023 |
Yes
| £3,204.00 | £3,765.00 | |
| Garage Door - Lathams Security Steel Door | 25/04/2023 | - |
Yes
| £467.00 | £549.00 | |
| Structural Work - Big breaker hire, windows, blocking, lintels, screeding | 02/05/2023 | - |
Yes
| £3,307.00 | £3,885.00 | |
| Plastering extras - Dot & dab, make good, encasement | 15/05/2023 | - |
Yes
| £6,620.00 | £6,620.00 | |
| Rendering - External finish, reveals, removed SVPs | 10/07/2023 | - |
Yes
| £1,200.00 | £1,200.00 | |
| Exterior Decoration - Re-paint entire property inc annexeNew | 20/08/2023 | - |
Yes
| - | £6,463.00 | |
| Technology - 3no. Ubiquiti WiFi 6 Pro access points & PoE switchNew | 28/08/2023 | 15/09/2023 |
Yes
| £473.00 | £555.00 | |
| Front Wall - Marshalls stone, pier caps, materials, lightingNew | 12/10/2023 | - |
Pending
| - | £4,469.00 | |
| Total Extras | £49,660.00 | |||||
Images & Reference
Notes
Images & Reference
Items & Costs
| Room | Supplier | Specification | PC Sum | Estimated Cost | Price to Client |
|---|---|---|---|---|---|
| Master Ensuite | Bathroom Elegance / Ripples | Full sanitary ware package | £7,018.00 | £4,211.00 | |
| Ensuite 2 | Bathroom Elegance / Ripples | Full sanitary ware package | £4,838.00 | £2,903.00 | |
| Ensuite 3 | Bathroom Elegance / Ripples | Full sanitary ware package | £4,995.00 | £2,997.00 | |
| WC | Bathroom Elegance / Ripples | WC suite | £1,393.00 | £836.00 |
Notes
Images & Reference
Items & Costs
| Item | Supplier | Specification | PC Sum | Estimated Cost | Price to Client |
|---|---|---|---|---|---|
| Primary Bathroom | Bottega Caliza 45x120 | Porcelanosa | 28 tiles | £2,010.00 | |
| Primary Bathroom | Spiga Bottega Caliza 45x120 | Porcelanosa | 4 tiles | £319.00 | |
| Ensuite 2 | Bottega Caliza 45x120 | Porcelanosa | 14 tiles | £1,005.00 | |
| Ensuite 3 | Bottega Caliza 45x120 | Porcelanosa | 12 tiles | £862.00 | |
| WC | Welsh Porcelain Slate Cardiff White | Porcelanosa | Floor only | £162.00 |
Notes
Images & Reference
Notes
Images & Reference
Notes
Images & Reference
Items & Costs
| Item | Supplier | Specification | PC Sum | Estimated Cost | Price to Client |
|---|---|---|---|---|---|
| Option 1 | Dining Room | 2-part sliding, Rosewood on White PVCu | Adam Windows | £5,995.00 | £4,996.00 |
| Option 2 | Lounge / Study / Kitchen | Sliding + flat windows, Rosewood on White PVCu | Adam Windows | £12,315.00 | £10,263.00 |
| Option 3 | Bedrooms | Flat windows, Rosewood on White PVCu | Adam Windows | £11,220.00 | £9,350.00 |
| Rooflight | Hallway | Flat glass rooflight 060060 | Velux | £2,017.00 | £2,017.00 |
Notes
Images & Reference
Items & Costs
| Item | Supplier | Specification | PC Sum | Estimated Cost | Price to Client |
|---|---|---|---|---|---|
| Living Room (Glazed) | 1981 x 762 x 35mm | Bolection Iris Oak, Glazed | Todd Doors | £261.00 | |
| Living Room (Nr Kitchen) | 1981 x 838 x 35mm | Bolection Iris Oak, Glazed | Todd Doors | £261.00 | |
| Kitchen (FD30) | 1981 x 838 x 44mm | Bolection Iris Oak, Fire Door | Todd Doors | £179.00 | |
| Study / WC / Bedrooms (x6) | Various | Bolection Iris Oak | Todd Doors | £179.00 each | |
| Hallway Cupboards (x6) | Various | Concealed Flush Primed | Direct Doors / Rocket | £399.00 |
Notes
Images & Reference
Notes
Client Details
Project Details
Client Brief
This specification sheet is based on an initial meeting with Robert Richman on Tuesday 11th Oct 2022.
And a subsequent meeting with Rob & Nicole on Monday 31st October 2022, & on Wed 16th Nov 2022.
This spec is based on the original plan although the client has provided a new upstairs layout which he is aware will impact on certain prices below.
We have compiled this job spec based on your current requirements however, should you wish to make any amendments post project commencement, these will be detailed in an additional services sheet with the relevant additions / subtractions to the price.
Due to the on going pandemic and the subsequent issues to the global supply chain, we will endeavour to make the client aware at the earliest opportunity of any price increases to materials which cannot be reasonably absorbed within the original contract price.
If Asbestos is found during the contract this is chargeable, for safe removal and disposal by Approved Asbestos Contractors.
We have provided a nominal figure for the number skips required to complete the job, however should more be required this will be at the client's cost.
TENDER PROCESS
- ESTIMATE STAGE - Based on 1 site visit and brief discussions with client
- SPECIFICATION STAGE - Following a further site visit and detailed discussion with client, including any visits to preferred suppliers
- FINAL SPEC & CONTRACT - Once client is completely satisfied with full spec for the project
Schedule of Works
| Phase | Description | Start | End | |
|---|---|---|---|---|
Services Specification
General Costs
| Name | Supplier | Est cost/quote | Final Cost | Price to client | |
|---|---|---|---|---|---|
| Muckaway | Supplier... | ||||
| Waste Removal | Supplier... | ||||
| Plasterboard Removal | Supplier... | ||||
| Inert Waste Removal | Supplier... | ||||
| Asbestos Pre-Refurbishment Survey & Removal | Supplier... | ||||
| WC - Welfare Facilities | Supplier... | ||||
| Site Security - Heras Panels with Stabilisers, Feet & Clips | Supplier... | ||||
| Tree Protection (Ground Guard) | Supplier... | ||||
| Bat Conservation | Supplier... | ||||
| Drainage Survey - CCTV | Supplier... | ||||
| Lifting / Propping Equipment (Cranes, Hi-Abs & Genie Lifts) | Supplier... | ||||
| Plant Hire (Diggers & Dumpers, Forklifts, Concrete Pumps) | Supplier... | ||||
| Scaffolding | Supplier... | ||||
| Floor Protection | Supplier... | ||||
| Property Services (Gas, Electric, Water - new connections & meter moves) | Supplier... | ||||
| Building Inspection | Supplier... | ||||
| CDM - Fire Risk Management Plan | Supplier... | ||||
| Total (included items) | £0.00 | £0.00 | £0.00 | ||
Labour
- General day to day site labour, waste management, meeting deliveries & tidying
- Strip wallpaper from any rooms
- Remove & dispose of curtains, tracks, blinds
- Remove & dispose of any skirtings, architraves, window boards & plastic trim
- Remove & dispose of all internal doors and door furniture
- Remove & dispose of existing kitchen & utility units, worktop and appliances
- Remove & dispose of WC, bathroom, ensuites sanitary ware
- Remove & dispose of all electrical fixtures, fittings, lighting and heating connections
- Remove & dispose of floor coverings ie carpet, underlay, old laminate / vinyl flooring
- Remove and dispose of all wall / floor tiles
- Driveway protection - OSB
- Install Heras fencing to perimeter
- Excavate to required depth and dig footings
- Use shuttering timber if required to sides of footings
- Pour concrete footings
- Install foul drainage connections
- Connections for Rain Water drainage
- Lay blockwork sub-structure
- Lay concrete blinding layer
- Install block and beam sub-floor
- Install ground bearing slab
- Build internal walls from lightweight thermalite blocks
- Build external walls from brick and dense blockwork
- Install steel beams as specified by Structural Engineer drawings
- Create new roof structure, including ashlar walls and 1st floor joists
- Lateral restraint to be provided with 30x5 galvanised MS restraint straps
- Openings for Velux windows in roof as per plan
- Construct Dormer as per spec
- Build flat roof as per spec including insulation
- Fit fascia board and soffit, fascia and corners
- Fix guttering and connect downpipes
- Soffit ventilation
- Strip roof and remove and dispose of tiles, felt and batten
- Install membrane and fit battens
- Flat roofing - single ply membrane
No default descriptions. Add one below.
No default descriptions. Add one below.
No default descriptions. Add one below.
No default descriptions. Add one below.
- Make safe electrics and connect temp site power
- Run all new electric cables from fuseboard to sockets and switches
- Install Switch & Socket Outlets
- Install Dimmer Switches
- Install Shaver / Mirror Light
- Install Recessed Lighting
- Install Wall & Pendant Lighting
- Install Under Cabinet Lighting
- Install 5amp Lighting
- Install Staircase Lighting
- Install Niche Lighting
- Install Fire & Smoke Safety
- Install Telephone / Internet / Networking
- Install TV Points
- Install TV & Soundbar
- Install Speakers
- Complete Earth Bonding
- Install Fuseboard
- Install Ceiling Fans
- Install External Lighting
- Install External Power Points
- Install Satellite Dish and connect LNB
No default descriptions. Add one below.
- Hob - Extraction
- Bathroom, Ensuite, WC, Utility - Extraction
No default descriptions. Add one below.
- Install temporary water supply
- Hot & Cold pipework supplies to kitchen, bathroom, ensuite, WC, utility
- Waste pipework connections for kitchen, bathroom, ensuite, WC, utility
- Connect kitchen / utility sink to waste pipework and install tap
- Connect outside tap
- Drain down existing heating circuit
- Drain Water storage tank
- Cut off Gas supply
- Install flow and returns to boiler
- Hang boiler and connect flue, gas and heating pipework
- Connections for water storage cylinder
- Hang new radiators and fit TRVs
- Hang and connect towel radiators
- Commission boiler, and balance heating systems
- Check all gas supplies and complete Gas Safe test and completion certificate
- Lay shower tray and fit to waste pipework
- Install wall hung WC frame and connect waste
- Fit bath / shower and screen, basin & tap, WC and seat
- Install Twin tank water softener & pipework
- Install Monarch Scale-out
- Install Aquabion inline scale reducer
- Install floor joists
- Install ceiling joists
- Install caber flooring
- Install Studwork
- Install boxings for bathroom / ensuite / WC
- Install door linings
- Install staircase, handrail and balustrade
- Install window boards
- Fit skirting
- Fit architrave
- Hang internal doors
- Fit handles, hinges, latches, locks, turns, bolts
- Fit door stops
- Trim doors to suit flooring
- Install external door frame and hang door
- Install steel security door
- Dry-fit kitchen and utility base units and wall cupboards
- Install worktop
- Fit appliances
- Cut and fix plinth to suit flooring
- Apply bonding coat and hardwall all cable / plumbing chases
- Make good, prep and plaster rooms complete
- Install m/f ceiling
- Studwork to have fibre glass / acoustic insulation
No default descriptions. Add one below.
No default descriptions. Add one below.
- Install internal wall or ceiling hung units
- Install external fan units
- Install RJ45 networking cable
No default descriptions. Add one below.
No default descriptions. Add one below.
- Part tile
- Fully tile
- Fit tile trims
- Wardrobes
- Bookcases
- Shelving
- Alcove units
- Install underlay and lay Luxury Vinyl Tile (LVT)
- Install underlay and lay carpet
- Fit anti-fracture matting and lay stone tiles
- Prepare and spray mist-coat of white contract emulsion to all new plastered walls and ceilings
- 2no. top coats of vinyl matt emulsion to all walls
- 2no. top coats of fast matt emulsion to all ceilings
- Undercoat & 2no. top coats of satinwood to all woodwork
- All internal doors come UNFINISHED so decoration is required
- Clean and prep area for sealant
- Supply & fit coloured sealant to kitchen, bathroom, wc, ensuite and window edges
- Professional builders clean of working areas
- Leave property ready for clients to move in
Materials
- Tough tubs, shovel, brush, gloves & hand tools
- Demolish existing
- Clear rubble to muck-away pile
- OSB - Shuttering Ply
- Soakaway crates, thuram
- Manholes, inspection chambers & rodding access points
- Pipe, bends, traps & connectors
- Facing bricks
- Heavy duty 7N dense blocks
- Lightweight blocks
- Concrete commons & engineering bricks
- Build sundries - Sand, Cement, Mortar Plasticiser, DPM, Weep vents, wall ties, DPC, Expansion roll
- Cavity fill concrete
- Mesh & rebar
- Type 1 & sand blinding
- Concrete
- Cavity closers
- Cavity insulation
- Air bricks
- Padstones
- Steel beams
- Concrete beams
- Insulated Catnic lintels
- Roof rafters
- Floor joists
- Fascia board
- Carpentry - Roofing sundries (joist hangars, lateral restraint & twisted straps)
- Hollow soffit board
- Fascia board
- Guttering
- Downpipes
- Joiners, outlets, clips
- Roof tiles
- Roof materials
- Flat roof covering
- Leadwork
- Roof vent tiles
- Roof vent systems
- Cladding
- Windows
- Sliding, patio, bi-fold doors
- Rooflights, skylights & lanterns
- Glass panels
- Mirrors
- Splashbacks
- Leadwork
- Insulation
- Vapour barrier
- Floor screed
- Primer, castellated panels, PERT pipe, edging strip
- Manifolds, actuators, pump/blenders & valves
- Heatmiser Neostat thermostats & wiring centres
- Heatmiser Neo Hub
- Switch & socket outlets
- Dimmer switches
- Shaver / mirror light
- Recessed lighting
- Wall & pendant lighting
- Under cabinet lighting
- 5amp lighting
- Staircase lighting
- Niche lighting
- Fire & smoke safety
- Telephone / internet / networking
- TV points
- TV & soundbar
- Speakers
- Earth bonding
- Fuseboard
- Ceiling fans
- External lighting
- External power points
- Antenna / aerial connections
- Satellite dish connections
- Alarm system, keypad, keyfobs, PIR, internal / external sounder
- Extractor fans
- Kitchen hob extraction
- Multiple room MEV units
- Heat pump
- Solar cylinder
- Solar panels
- Inverter
- Battery storage
- Car chargers
- MLCP pipe, connectors, valves, tees, bends, reducers
- Waste pipework, solvent
- Boiler
- Cylinder
- Radiators
- TRV & lockshield valves
- Showers, screens, baths, basin units, taps, wastes, WC, towel rads
- Kinetico Twintec water softener
- Monarch Scaleout
- Aquabion scale reducer
- 2x2, 3x2 & 4x2 CLS timber
- Caberdek flooring
- OSB / ply wood / shuttering timber
- Door linings
- Window boards
- Aquapanel / Hardy backer board / Wedi boards
- Skirting
- Architrave
- Timber door stop
- T&G panelling
- Kitchen, units, appliances
- Kitchen worktop & upstand
- Utility, units, appliances
- Utility worktop & upstand
- Internal doors
- Fire doors
- Glazed doors
- Cupboard doors
- Handles
- Hinges
- Latches
- Bath locks & turns
- Skirting / floor mounted door stops
- Front doors
- Sidelights
- Garage / side doors
- Plaster / moisture / fireline / foil back / soundbloc / insulated boards
- Plastering sundries (skrim tape, betokontakt, collated screws, thin coat angle beads)
- Multi-finish plaster, hardwall & bonding coat
- Perimeter channels, primary & furring sections, clip, hangars, angles, brackets
- Rigid PIR insulation
- Fibre glass insulation
- Acoustic insulation
- Loft roll
- Render - Washed plastering sand, cement and lime
- Render materials - Fibreglass mesh, stop/angle beads, mortar plasticiser, water proofer
- Gas / electric fire
- Fireplace surround / mantle piece
- Hearth
- Internal wall ceiling mounted units
- External fans
- Wi-Fi access points
- PoE router
- Video doorbell
- Outdoor cameras
- Treads, risers, stringers & newel posts & caps
- Handrail, balustrades, spindles
- Floor tiles
- Wall tiles
- Wardrobes
- Bookcases
- Alcove units
- Shelves
- Luxury Vinyl Tile & underlay
- Stone tiles & fracture matt
- Carpets & underlay, threshold & gripper bars
- Door mats
- Wall / ceiling paint - fast matt / vinyl matt
- Woodwork paint - water-based satin wood
- External / masonry paint
- Decorators sundries - sanding pads, caulk, tape, filler, knotting solution, brushes / rollers, varnish
- High modulus - interior, rigid, abrasion resistant
- Low modulus - exterior, flexible, PVC & expansion joints
- Knife, scraper, Henry Hoover, builder wipes, bucket / mop, micro-fibre cloths
- Screwfix, Strukta, Toolstation, Plumstop, B&Q etc
- Knife, scraper, Henry Hoover, builder wipes, bucket / mop, micro-fibre cloths
- Breakfasts or beers
Agreed Payment Milestones
| # | Milestone | Trigger | % | Net | inc VAT |
|---|---|---|---|---|---|
| 1 | Deposit | Due on acceptance of estimate | 60% | £127,308.00 | £148,526.00 |
| 2 | 1st Fix Complete | Electrics, plumbing, carpentry 1st fix signed off | 20% | £42,436.00 | £49,509.00 |
| 3 | Project Completion | All works complete, snagging signed off, handover | 20% | £42,436.00 | £49,509.00 |
| Total Contract Value | 100% | £212,180.00 | £247,544.00 | ||
Payment Terms
Payment Terms
Internal Margin
Set a margin rate per cost category (Labour, Materials, General Items). Each row's Price to Client is recalculated automatically from its Estimated Cost × that category's margin. This card is stripped from client-facing exports.
| Cost Category | Margin % | Estimated Cost | Margin (£) | Price to Client |
|---|---|---|---|---|
| Labour | % | £0.00 | £0.00 | £0.00 |
| Materials | % | £0.00 | £0.00 | £0.00 |
| General Items | % | £0.00 | £0.00 | £0.00 |
| Totals | £0.00 | £0.00 | £0.00 | |
Financial Summary
| Labour Total (Net) | £92,409.00 |
| Materials Total (Net) | £70,467.00 |
| General Items Total (Net) | £6,267.00 |
| Total Job Spend | £169,143.00 |
| Total Client Spend (inc Additional Services) | £213,737.00 |
| Actual Profit (inc fees on direct client payments) | £61,854.00 (28.94%) |
Items removed from original estimate - client paid suppliers directly. 17.5% WBP management fee applied.
| Sanitaryware | £17,500.00 |
| Kitchen | £17,000.00 |
| Utility | £7,800.00 |
| Flooring (LVT & Carpet) | £13,300.00 |
| Fenestration (French Doors / Sliders) | £16,675.00 |
Payment Schedule